Five Year Plan

Proposed – Nobles County Five Year Road Plan

Listed below are the proposed construction project set by the Nobles County Board of Commissioners for the next 5 years.
Construction Year 2015
Roadway Location Project Description
CSAH 39 CSAH 1 to Dundee-0.5 mile Bituminous Overlay
CSAH 39 Dundee – 0.75 mile Reconstruction and Overlay
CSAH 1 CSAH 18 to Co. Line.-2.35 miles Bituminous Overlay
CR 75 In Brewster – 0.37 mile Mill and Overlay Surface
CSAH 20 1.9 miles east CSAH 19 Bridge Replacement
CSAH 15 0.8 mile north of CSAH 30 Bridge Replacement
CSAH 14 City of Brewster Mill and Overlay Surface
Construction Year 2016
Roadway Location Project Description
CSAH 13 Iowa Line to CSAH 35 – 8.2 miles Bituminous Overlay
CSAH 6 CSAH 13 to CSAH 4 – 3.0 miles Bituminous Overlay
CSAH 15 CSAH 16 to Murray Co.-6.2 miles Bituminous Overlay
CSAH 16 TH 91 to CSAH 34 5.0 miles Bituminous Overlay
Construction year 2017
Roadway Location Project Description
CSAH 25 10 Ave to Oxford St – 0.25 mile Mill and Overlay Surface
CSAH 16 CSAH 25 to CSAH 9 – 4.0 miles Bituminous Overlay
CSAH 7 CSAH 18 south to CSAH 18 north Bituminous Overlay
CSAH 15 0.7 mile north of CSAH 14 Bridge Replacement
CSAH 13 0.1 mile North of CR 70 Bridge Replacement
CSAH 13 0.1 mile North of CR 69 Bridge Replacement
CR 70 0.7 mile East of CSAH 13 Bridge Replacement
CR 68 0.6 miles East of CSAH 15 Bridge Replacement
CSAH 18 CSAH 7 to TH 59 Bituminous Overlay
Construction year 2018
Roadway Location Project Description
CSAH 13 CSAH 25 to Murray Co.-6.7 miles Bituminous Overaly
CSAH 9 CSAH 25 to CSAH 18 – 7.0 miles Bituminous Overlay
CSAH 16 0.9 mile East of CSAH 1 Bridge Replacement
Construction year 2019
Roadway Location Project Description
CSAH 13 1-90 to CSAH 25 – 8.5 miles Bituminous Overlay
CSAH 3 CSAH 14 to CSAH 16 5.0 miles Bituminous Overlay
CSAH 21 CSAH 3 to CR 51 south section Reconstruction